Zaheer Ikbal, Founder, CyHelm
A lot of risk registers have a few rows that say “Accepted.” A lot of exception logs have a few that say “Approved.” Ask who accepted it, on what basis, and when anyone will look at it again, and the room often goes quiet.
That quiet is the problem. An acceptance with no name and no end date is just a risk that nobody is managing.
ISO/IEC 27001 is specific about who accepts risk and on what basis. It doesn’t mention exceptions or expiry dates. Those are good practice, and the fix doesn’t need a tool. It needs a few columns and some discipline.
What the standard actually asks for
Two clauses do the work.
Clause 6.1.2 says your risk assessment process has to establish and maintain risk criteria that include “the risk acceptance criteria,” and it has to “identify the risk owners.”
The last step in clause 6.1.3, item f), is the line I’d ask every ISMS owner to reread. The organization shall:
“obtain risk owners’ approval of the information security risk treatment plan and acceptance of the residual information security risks.”
Two things stand out.
First, it’s the risk owner who approves and accepts. That isn’t the IT manager just because the system sits in IT, or the security lead just because they wrote the register. The person who owns the risk has to own the decision.
Second, residual risk acceptance isn’t only for the risks you decided to “accept.” Every risk you treat still has something left over after the controls are in. The standard wants the owner to accept that remainder too. So the better question to ask is whether every residual risk has been accepted by the right person.
Risk acceptance and exceptions aren’t the same thing
These two get mixed up, and it causes trouble.
- Risk acceptance is a decision about a risk. The owner looks at the residual risk, compares it with your acceptance criteria, and decides to live with it.
- An exception is a decision about a rule. Your policy says one thing, and a system, team or supplier can’t meet it yet. Someone approves the gap.
Every exception creates a risk, so it should point to a risk in the register. But an exception should always be temporary. If you find yourself approving the same exception year after year, either the policy is wrong and needs changing, or the risk should be assessed and accepted properly as a risk, with an owner and a review date.
NIST’s Cybersecurity Framework 2.0 names exceptions explicitly, in the same outcome as changes. Subcategory ID.RA-07 reads: “Changes and exceptions are managed, assessed for risk impact, recorded, and tracked.” NIST’s implementation examples for it include documenting “the risks related to each requested exception and the plan for responding to those risks,” and periodically reviewing “risks that were accepted based upon planned future actions or milestones.” CSF is voluntary, but those two lines are a good test for any exceptions log.
The columns I’d put in the register
You can run this in the risk register you already have, or in a separate exceptions log linked to it. The standard doesn’t prescribe columns; these are the ones I’d use. Either way, each row needs:
- Reference and link. An ID, and the risk or policy clause it relates to.
- What’s being accepted, in plain words. “Finance’s legacy payroll server can’t run the current endpoint agent,” not “EDR gap.”
- Why. The business reason. Cost, a vendor dependency, a project that isn’t finished.
- Residual risk rating. Scored with the same method as everything else, with a note of whether it’s inside your acceptance criteria.
- Risk owner. A named person and role, with the authority to accept that level of risk.
- Interim measures. What reduces the exposure in the meantime, if anything, who runs them, and how you check they’re working.
- Date accepted and expiry date. Both. No blank expiry.
- Review date and reviewer. When it comes back, and who brings it back.
- Exit condition. What has to happen for the row to close (the system is replaced, the control is in place, or the policy is formally changed), and its reference in the risk treatment plan.
- Status. Open, closed, expired, or renewed.
Columns 5, 7 and 9 are the ones that tend to go missing. Without them you’ve got a list, not a register.
Who’s allowed to say yes
Your acceptance criteria should say more than where the line sits. They should also say who can accept risk above it.
A simple ladder works for most small and mid-sized companies. Here’s an example you’d adapt to your own scoring and structure, not a rule from the standard:
- Low residual risk: the risk owner can accept it.
- Medium: the risk owner accepts, and the head of the function co-signs.
- High: a member of senior management.
- Above your acceptance criteria: the default is to treat it, not accept it. If top management decides to accept it anyway, record the decision, the reason and a short expiry, and treat it as a case for revisiting the criteria or the treatment.
Whatever ladder you choose, write it into your risk acceptance criteria, so it’s part of the method and not a habit.
If your company has set risk appetite and tolerance statements, tie the ladder to them. CSF 2.0 has a separate outcome for establishing, communicating and maintaining those statements (GV.RM-02).
The point is that whoever signs can actually live with the consequences. If the risk is a week of lost invoicing, the person accepting it should be someone who’d answer for a week of lost invoicing.
When the real fix has to wait
This is where most exceptions come from. The proper fix is in next year’s budget, or depends on a vendor upgrade that hasn’t shipped yet.
That’s fine, as long as whatever you do in the meantime is written down as what it is: a temporary measure, not the fix. For that payroll server, you might put it on its own network segment, limit who can log on, and review its logs weekly until it’s replaced. Those steps reduce the exposure. They don’t remove it.
Give the interim measure an owner, a reason and an expiry date, and set a review date before that expiry, so it doesn’t lapse quietly. Name the permanent fix it’s waiting for, with its own owner and target date in the treatment plan. When the expiry date comes, one of three things happens:
- The permanent fix is in, and the row closes.
- The owner reviews it again and re-accepts the residual risk on the record, with a new expiry date and a reason for the extension. A second renewal goes one step up the approval ladder.
- Nobody acts, and the row shows as expired. An expired acceptance isn’t still accepted. It goes back to the owner and up to management, and it stays open until someone decides. The interim measures stay in place while it’s decided.
Renewing is fine, as long as it’s on the record.
Keep the register alive
A register that gets updated once a year, the week before the audit, won’t tell you much. A small routine keeps it honest:
- Monthly: pull every row expiring in the next 60 days and send each owner a reminder.
- When something changes: a new system, a new supplier, a project slipping. Check whether any acceptance relied on the old situation.
- Management review: report the totals. How many acceptances and exceptions are open, how many expired, how many were renewed more than once, and which ones sit above appetite. Repeat renewals are the ones to talk about.
Write down what was decided
When an acceptance is granted, renewed or closed, write it down: the date, the risk, the residual rating, the owner who accepted it and anyone who co-signed, the expiry and the reason. Clause 6.1.3 also says the organization shall retain documented information about the risk treatment process, so a record like this is the obvious evidence.
That entry is a record of a decision. It isn’t a control or a procedure, and it doesn’t reduce the risk on its own. Its job is to answer the question at the top of this article, months later, for someone who wasn’t in the room: who accepted this risk, and until when?
If you can answer that for every row, your register is doing its job.
Sources
- ISO, ISO/IEC 27001:2022 Information security management systems — Requirements: https://www.iso.org/standard/27001
- ISO/IEC 27001:2022 preview, iTeh Standards (text of clauses 6.1.2 and 6.1.3): https://cdn.standards.iteh.ai/samples/82875/726bcf58250e43d9a666b4d929c8fbdb/ISO-IEC-27001-2022.pdf
- NIST, The NIST Cybersecurity Framework (CSF) 2.0, CSWP 29 (26 Feb 2024): https://nvlpubs.nist.gov/nistpubs/CSWP/NIST.CSWP.29.pdf
- NIST, CSF 2.0 Implementation Examples (26 Feb 2024): https://www.nist.gov/system/files/documents/2024/02/21/CSF%202.0%20Implementation%20Examples.pdf